Under 32 CFR § 170.21, a CMMC Level 2 POA&M is permitted only if your assessment score is at least 88 of 110 (0.8), every open item has a point value of 1 (the one exception is SC.L2-3.13.11 CUI encryption that exists but isn’t FIPS-validated), six named requirements are fully met, and everything is closed and verified within 180 days of the Conditional status date. Level 1 allows no POA&M at all.
Where the rules come from
CMMC’s POA&M limits are in the program rule, 32 CFR Part 170, specifically § 170.21 (Plan of Action and Milestones requirements). They are deliberately stricter than the open-ended POA&M that DFARS 252.204-7012 tolerated for years. Under CMMC, a POA&M is a short bridge to a certificate, not a place for hard requirements to live indefinitely.
The July 2026 suspension of CMMC Phase 2 (mandatory C3PAO certification) did not amend 32 CFR Part 170, so these POA&M rules still govern every Level 2 self-assessment and every voluntary C3PAO assessment today. The CMMC Reform Task Force could recommend changes; until a rule change is published, this is the standard.
Level 1: no POA&M, ever
The rule is one sentence: “A POA&M is not permitted at any time for Level 1 self-assessments.” All 15 requirements must be MET to claim Level 1 status. If one isn’t, you don’t have Level 1 — you have a to-do list.
Level 2: the four tests a POA&M must pass
| # | Test | What it means in practice |
|---|---|---|
| 1 | Minimum score ≥ 0.8 — assessment score ÷ 110 must be at least 0.8 | At least 88 points. Because requirements are weighted 5, 3, or 1, a handful of open 5-pointers can put you under 88 even with “most” requirements met. |
| 2 | No open item worth more than 1 point | Every 3-point and 5-point requirement must be MET. The single exception is SC.L2-3.13.11 (see below). |
| 3 | Six specific requirements must be MET regardless of point value | Listed in the next section. They’re 1-point items the DoD considers foundational. |
| 4 | Closed and verified within 180 days | A POA&M closeout assessment — by the C3PAO for a C3PAO certification — must confirm every open item is now MET within 180 days of the Conditional CMMC Status Date. |
The six requirements that can never be on a POA&M
| Requirement | Name | Why it’s excluded |
|---|---|---|
| AC.L2-3.1.20 | External Connections | You must know and control every connection to external systems before anything else is credible. |
| AC.L2-3.1.22 | Control Public Information | Prevents CUI being posted to public-facing systems — a leak, not a gap. |
| CA.L2-3.12.4 | System Security Plan | The SSP is the document the entire assessment is scored against. No SSP, no assessment. |
| PE.L2-3.10.3 | Escort Visitors | Basic physical protection; the DoD considers these achievable by any organization immediately. |
| PE.L2-3.10.4 | Physical Access Logs | |
| PE.L2-3.10.5 | Manage Physical Access |
The one exception: non-FIPS encryption
SC.L2-3.13.11 — Employ FIPS-validated cryptography to protect the confidentiality of CUI — is a 5-point requirement. The rule allows it on a POA&M in exactly one situation: encryption is in place but the cryptographic module isn’t FIPS-validated. In that case the deduction is 3 points instead of 5, and the item may be deferred. If CUI isn’t encrypted at all, the full 5 points come off and the item can’t be on the POA&M.
This exception exists because replacing an encryption product is a procurement problem as much as a security one. It does not mean non-FIPS encryption is acceptable — the item still has to be closed within 180 days.
A quick refresher on how the score works
- Start at 110. Each NOT MET requirement subtracts its weight: 5 points for the most critical, 3 for the significant, 1 for the rest.
- Two partial-credit cases exist: 3.13.11 (non-FIPS encryption, −3 instead of −5) and 3.5.3 (MFA implemented for remote and privileged users but not general users, −3 instead of −5).
- The minimum possible score is −203. Yes, negative scores are real and are recorded in SPRS.
- A requirement is MET only when all of its assessment objectives in NIST SP 800-171A are met. Partially implemented is NOT MET.
Conditional vs. Final status
If you pass the four tests, the C3PAO issues Conditional Level 2 (C3PAO) status and the clock starts. Close every item, have the closeout assessment confirm it, and the status becomes Final, valid for three years from the Conditional date — the 180 days are not added on. Miss the 180-day window and the Conditional status lapses; you’re back to remediation and a new assessment. Contracting officers can see Conditional status in SPRS and some will not award against it, so treat Conditional as a deadline, not a certificate.
Practical guidance
- Don’t plan around a POA&M. Plan to pass clean. The POA&M is for the two or three 1-point items that slipped in the last month — a procedure not yet fully exercised, a review cycle with one gap.
- Knock out all 5-point and 3-point items first. They can’t be deferred, and they carry the score. Check the DoD Assessment Methodology scoring table while you prioritize.
- Lock the six excluded requirements early. An SSP, external-connection inventory, public-information review, and visitor/physical-access procedures are weeks of work, not months. There’s no reason for any of them to be open at assessment.
- Pre-write the closeout plan. If you do take Conditional status, the C3PAO must come back. Schedule that closeout assessment the same week you receive the Conditional result — their calendar won’t wait for you.
- Match the POA&M to the SSP. Assessors read both. A POA&M item that the SSP claims is implemented is a credibility problem for every other claim in the SSP.